Maintenance in Trinity, FL

Published on: Friday, March 26, 2021 at 12:15 pm

Summary:

System: Seven Springs

Customers Impacted: 410

Effective Date: March 29, 2021

Completion Date: October 6, 2021

Detailed Info:

Thursday, October 7, 2021: The FGUA’s Cross Connection Control Program has been completed.

Wednesday, May 26, 2021: The FGUA’s Cross Connection Control Program in Thousand Oaks East has recommenced following a temporary suspension of work.

Monday, May 17, 2021: The FGUA’s Cross Connection Control Program in Thousand Oaks East has been temporarily suspended. Please check back for updates.

Originally Posted: March 26, 2021, 12:15 p.m.

Schedule Updated: Tuesday, June 1, 2021, 4:50 p.m.

Beginning Monday, March 29, 2021, the FGUA will begin retrofitting potable water meters in the Thousand Oaks East community in Trinity, Florida by installing new backflow prevention devices on the potable water meter that will fit within the potable meter box. The retrofitting ensures that each customer meets all Federal and State drinking water safety standards. Backflow is an unplanned reverse flow of water that can cause serious health concerns from possible contaminated water on the customer’s side of the potable metered connection. Installation of the backflow device ensures that a reverse flow does not occur or contaminate the public water system.

Customers will receive a door hanger with information concerning the backflow installation at least 48 hours before work begins on their meter. During this installation process, customers may expect a 45-minute interruption of service. Prior to the retrofitting on each property, an FGUA Representative will provide a courtesy knock. Once service is restored, customers may resume water use as desired, as no Precautionary Boil Water Notices are needed for this service improvement.

The program schedule with proposed and actual schedules is noted below. Please be advised, the schedule is subject to change due to weather, environmental factors, physical factors in the utility right of way, and emergencies.

Street Number of Locations Installed Remaining Anticipated Start Date Anticipated End Date Anticipated Duration (days) Actual Start Date Actual End Date
Regal Mist Loop 80 80 0 3/29/2021 4/22/2021 19 3/30/2021 4/23/2021
Gallberry Court 28 28 0 4/6/2021 4/12/2021 5 4/5/2021 4/13/2021
Lenton Rose Court 33 33 0 4/23/2021 5/28/2021 26 4/23/2021 5/27/2021
Kaffir Lily Court 27 27 0 6/1/2021 6/18/2021 14 5/26/2021 6/18/2021
Impatiens Court 23 23 0 6/21/2021 6/24/2021 4 6/16/2021 6/24/2021
Amaryllis Court 27 27 0 6/25/2021 7/1/2021 5 6/24/2021 6/25/2021
African Violet Court 29 29 0 6/28/2021 7/2/2021 5 6/28/2021 6/30/2021
Swamp Rose Lane 41 41 0 7/5/2021 7/28/2021 18 6/30/2021 7/26/2021
Pink Guara Court 51 51 0 7/8/2021 7/22/2021 11 7/1/2021 7/15/2021
Sumac Court 11 11 0 7/9/2021 10/15/2021 71 7/12/2021 10/4/2021
Sweetspire Drive 60 60 0 7/29/2021 10/15/2021 57 7/26/2021 10/4/2021
9040 Tryfon Blvd. 5 5 0 10/4/2021 10/8/2021 4 10/6/2021 10/6/2021