Plantation Bay Water and Wastewater Treatment Plant

Project Information

  • Summary – The FGUA is constructing a new 0.4 Million Gallons per Day (MGD) Water Treatment Plant (WTP) and a 0.5 MGD Wastewater Treatment Plant (WWTP) at the Plantation Bay Facility. These projects replace facilities that have exceeded their useful life.
  • Project Funding – This project is funded by a combination of grants and loans.
  • Construction – The Wastewater Treatment Plant (WWTP) is online and substantially complete. Punch list items are being addressed. Ferreira Construction Company is the low bidder for the Water Treatment Plant (WTP). Anticipated completion of this project is early 2027. 
  • Public Meeting – Currently no public meetings are scheduled. Two public meetings were held at the end of 2025.
  • FGUA Contacts – Please see below.


PM Phone
: 360-522-3008
Project Manager: Mike Whitfield – mike.whitfield@fgua.com

0.4 MGD Water Treatment Plant (WTP)

WT Drawing
Skids Schematic

0.5 MGD Wastewater Treatment Plant (WWTP)

USW Drawing
Picture1
Picture2

Project Updates

  • Latest Activities:

    • Delivery of the Mobile Office Trailer – Complete.
    • Surveying – Complete.
    • Submittals – Submittals for materials being ordered, awaiting submittal log with dates.  This is an ongoing process with a 4 week look ahead schedule.
    • Safety Plan for Contractor Personnel Safety – Plans received on 2/25/25, uploaded into Autodesk.
    • Hurricane Plan for Site and Personnel Safety During Inclement Weather – Received plan on 2/25/2026, uploaded into Autodesk.
    • Submittal Log for Materials Order, Engineering Review, Order Dates, and Delivery Dates – Jones Edmonds maintains an updated submittal log.  
    • Concrete – Complete.
    • Structural Building – Complete.
    • All Project Piping – Complete.
    • Chemical Tanks  – Complete.
    • Hydro Tank  – Complete.
    • Mechanical and HVAC  – Complete.
    • Door and Roll-Up Door  – Complete.
    • Plumbing – Complete.


    Permitting and Regulatory Items:

    • Flagler County Building Permit – Complete, permit received in July 2026.
    • Dewatering Permit –   Complete.


    Additional Activities:

    • Exploratory Potholing to Locate Potential Underground Utilities – Complete.
    • Delivery of Civil Piping – Complete.

The FGUA held two Community Meetings at the end of 2025.

The October Community Meeting provided a status update for the program. The December Community Meeting hosted a Q & A session as requested during the October 2025 Community Meeting.

CLICK HERE to View/Download a copy of the December Community Meeting’s presentation.
CLICK HERE to View/Download a copy of the October Community Meeting’s presentation.

flyer front

flyer back

Skip to content