Project Title: DUP 12 (Chatmire Septic-to-Sewer) Project

System: Dunnellon Utility

Description:

FGUA is undertaking a septic to sewer project in the Chatmire community located in the City of Dunnellon.  The project will include 210 residential lots with approximately 117 existing septic systems, 14,000 linear feet of gravity sewer collection lines, 1,640 linear feet of force main, a new lift station, 16,000 linear feet of roadway restoration and abandonment of existing septic systems and connect to the central sewer system.  Construction of the new central sewer system is approximately 90% complete with only two (2) manholes remaining to be excavated and set  Construction of onsite sewer laterals and abandonment of septic tanks will commence in May 2024 upon completion of the associated sewer lift station.  The project will be complete by October 2024.

 

Picture1
Figure 1: Interior View of Chatmire Lift Station

 

Picture2
Figure 2: Rerouting Unknown 8-inch Water Main